The Presidential Power Initiative marks another milestone in its goal to modernize and rehabilitate the national grid infrastructure to deliver reliable and stable electricity to households and businesses across the country.
A delegation from FGN Power Company, led by the MD/CEO Mr. Kenny Anuwe, witnessed the Factory Acceptance Test (FAT) at Siemens Energy High-Voltage Transformer Lab in Trento, Italy for the approved Ten (10) Power Transformers and Ten (10) Mobile Substations under the Presidential Power Initiative.
The FAT aims to evaluate the equipment’s compliance with the functional requirements and verify that the required functional specifications are in line with the International Electro-technical Commission (IEC) standards. Also, the first two energy transformers have been manufactured and will be delivered in September 2022 under a strategy for quick