Siemens power deal phase one reaches 80% completion- FGN Power Company

Phase one of the Siemens power deal under the Presidential Power Initiative (PPI) is 80% complete according to the FGN Power Company. The pilot project which is described as a quick-win intervention strategy, aims to address immediate constraints in the Nigerian Electricity Supply Industry (NESI). The successful implementation of projects under Phase 1 is expected […]

Arrival of PPI’s Mobile Substation

The Presidential Power Initiative (PPI) project for Phase 1 is underway and has recorded notable successes. The Pilot Project is a quick-win intervention strategy which will unlock immediate constraints in the Nigerian Electricity Supply Industry (NESI) through the deployment of Ten (10) Power Transformers and Ten (10) Mobile Substations across the country. The Mobile Substation, […]

Apo Transformer Energization

FGN Power Company has completed the installation and energization of the 60MVA, 132/33kV power transformer at Apo Transmission Substation. The newly installed Apo transformer has replaced the 45 MVA 132/33 kV transformer that is no longer in service. This replacement will ensure steady and dependable supply at the transmission level to approximately 5,000 households and […]

Niger Delta Power Holding (NDPHC) Building 1490, Samuel Ademulegun Avenue,
Central Business District, Abuja, Nigeria

Explore the PPI

Copyright © 2023 FGN Power Company